问题 1:
(1)签约合同价:[48.36+48.36×(2.4%+1.6%)+5]×(1+8%)×(1+9%)=65.093(万元)
(2)材料预付款:[65.093-5×(1+8%)×(1+9%)]×20%=11.841(万元)
(3)安全文明施工费预付款:48.36×2.4%×(1+8%)×(1+9%)×90%=1.230(万元)
问题 2:
(1)原合同分部分项工程费用:4.32×2/3+4.80×1/4+5.52×2/5+6.75=13.038(万元)
(2)工作 G 材差:[(250-220×1.05)×67500×68%/200]×(1+10%)/10000=0.480(万
元)
(3)临时分项工程 M 工程费用:(1.2+3.5+1.0)×(1+10%)=6.270(万元)
(4)除安全文明施工外的总价措施费用:(13.038+0.480+6.27)×1.6%=0.317(万元)
(5)已完工程进度款:(13.038+0.480+6.27+0.317)×(1+8%)×(1+9%)=23.668(万元)
(6)应支付工程进度款:23.668×90%-11.841/2=15.381(万元)
问题 3:
销项税:(1.2+3.5+1.0)×(1+10%)×(1+8%)×9%=0.609(万元)
可抵扣增值税进项税:3.5×13%+1×5%=0.505 (万元)
应缴纳的增值税:0.609-0.505=0.104 (万元)
分项工程 M 的工程价款:
(1.2+3.5+1.0)×(1+10%)×(1+8%)×(1+9%)=7.381(万元)
问题 4:
(1)合同增减额:[0.480+6.27+(96×3/4+54×2/3)×(116-88)/10000×(1+10%)]×(1+4%)×(1+8%)×(1+9%)-5×(1+8%)×(1+9%)=2.785(万元)
(2)实际总造价:65.093+2.785=67.878(万元)
(3)竣工结算尾款:67.878×(1-3%-90%)=4.751(万元)