1.挖土方清单工程量:V =(6.9+4)×(6.6+4)×(1.4-0.3)=127.09(m3)
2.矩形柱:V =0.4×0.4 ×(0.8+3.3)×6=3.94(m3)
有梁板B-2(100):V 1=(3.3-0.125-0.13)×(4.2-0.13-0.125)×0.1=1.201(m3)V2 =(3.6-0.125-0.13)×(4.2-0.13-0.125)×0.1=1.32(m3)
B-2(80)(2.4-0.125-0.13)×(2.4-0.13-0.125)×0.08=0.368(m3)(图纸中缺少尺寸,数据仅供参考)
KL1:V =0.25×0.5×[(7.14-0.4×2)×3+(6.84-0.4×3)×2]=3.79(m3)
3.内墙:V =[(7.14-0.4×2)×(3.3-0.5)-0.9×2.1]×0.24=3.81(m3)
4.散水:外=(7.14+6.84)×2=27.96(m)
S =(27.96-1.68)×0.9+0.9×0.9×4 =26.89(m2)