1: (1)垫层:2×2×0.1×17=6.8m3 (2)独立基础:(1.8×1.8×0.4+1×1×0.4)×17=28.83 m3
(3) 基础梁: 0.25×0.5×(4.8-0.4)[A轴]+0.25×0.5×(19.2-0.4×4)×3[BCD轴]+0.25×0.5×(7.2-0.4×2)×3[①②③轴] +0.25×0.5×(10.8-0.4×3)×2[④⑤轴] =11.95 m3
(4) 柱:0.4×0.4×(3.6+2-0.8)×17=8.16 m3
(5)过梁:0.24×0.18×(2.4+0.25×2)×10=1.25 m3
(6)楼板: (4.8-0.1-0.15)×(3.6-0.1-0.15)×0.12×3+(4.8-0.15 ×2)×(3.6-0.1-0.15)×0.12×4+(4.8-0.1-0.15)×(3.6-0.15×2)×0.12+(4.8-0.1-0.1)×(3.6-0.1-0.15)×0.12 =16.37 m3
(7)整体地面:
(19.6-0.24 ×2)×(7.6-0.24×2)+3.6×(4.8+0.4-0.24×2)=153.99㎡
(8)吊顶天棚:
(19.6-0.24 ×2)×(7.6-0.24×2)+3.6×(4.8+0.4-0.24×2)=153.99㎡
2:表6.Ⅰ.3 工程量清单综合单价分析表
工程名称: 某钢筋混凝土框架结构工程 标段: